🚆|Main contractor Balfour Beatty Vinci (BBV) has abandoned proposals to use concrete retaining walls along a small section of track in Warwickshire.
The redesign removes the need to excavate 150,000m3 of soil and requires 60,000m3 less concrete and steel.
To find out more, follow the link below: